13th Feb’ 2007
|
-
Commencement of land acquisition
|
Aug’ 2007
|
-
Preparatory construction work commenced
|
Feb’ 2009
|
-
Actual Construction of Factory started
|
May’ 2010
|
-
Commissioning of 33 KV Transmission Line
|
Jan’ 2011
|
-
Finishing & Furnishing shop work completed
|
April’2011
|
-
First Coach Furnished from shell supplied by RCF/KXH
|
April’2011
|
|
April’ 2011
|
-
Furnishing of 1st LWSCZAC (Chair Car)
|
June; 2012
|
-
Furnishing of 1st LWFCZAC (Ex. Chair Car)
|
July’ 2012
|
-
Dedication of Factory to the Nation
|
Nov’ 2012
|
-
Furnishing of 1st LWACCW Coach
|
Nov’ 2012
|
-
First Shell Assembly (Major sub assembly by RCF/KXH)
|
July’ 2013
|
|
July’ 2013
|
-
Assembly of First LHB coach shell by MCF
|
July’ 2013
|
|
Feb’ 2014
|
-
Completion of Shell, Paint and Machine Shops
|
Mar’ 2014
|
|
April’ 2014
|
-
Manufacture of first prototype fabricated Fiat Bogie
|
Aug’ 2014
|
-
Manufacture of first LHB coach shell by RCF/RBL
|
Aug’ 2014
|
-
Furnishing of 1st LWSCN COACH
|
Sep’ 2014
|
-
Completion of Administrative Building
|
Nov’ 2014
|
|
Dec’ 2014
|
-
Manufacture of first Fiat bogie
|
Dec’ 2014
|
-
Commissioning of 132 KV MRS
|
Jan’ 2015
|
|
Feb’ 2015
|
-
100th Shell, Manufactured
|
June’ 2015
|
-
1st LSCN Shell, Manufactured
|
July’ 2015
|
|
Dec’ 2015
|
-
RCF, Raebareli Renamed (MCF), Raebareli
|
Dec’ 2015
|
-
300th LWACCN Coach Furnished
|
Jan’ 2016
|
|
Feb’ 2016
|
-
1st GS Shell Manufactured
|
April’ 2016
|
-
Formed Recognised Technical Training Centre
|
May’ 2016
|
|
Oct’ 2016
|
|
Oct’ 2016
|
-
1st Rake of Humsafar coaches dispatch
|
Nov’ 2016
|
|
Jan’ 2017
|
-
1st Rake of Antyodaya Coaches dispatch
|
April’ 2017
|
-
1st Power Car Shell manufactured
|
May’ 2017
|
-
1000th Shell manufactured
|
May’ 2017
|
-
5th Rake of Humsafar coaches dispatched
|
June’ 2017
|
-
1st Power Car handed over to ZR
|
Oct, 2017
|
|
Oct’ 2017
|
-
1st Coach of Deen Dayalu dispatched
|
Jan’ 2018
|
-
Total 25 nos. Power Car handed over to ZR
|
Mar’ 2018
|
|
May’ 2018
|
-
1st SMART Coach dispatched
|
May’ 2018
|
-
1st LHB Under Slung LDSLR Coach turned out
|
Jan’ 2019
|
-
1st LHB AC Pantry car turned out
|
Jan’ 2019
|
-
1st LHB Non-AC Chair Car turned out
|
Feb’ 2019
|
-
1st LHB Track Recording Car turned out
|
Mar’ 2019
|
-
Green Co Platinum Rating Conferred to MCF
|
June’ 2019
|
-
1st LHB First AC Coach turned out
|
Aug’ 2019
|
|
Aug’ 2019
|
-
1st Smart Humsafar rake of Indian Railways dispatch
|
17th Feb’ 2020
|
|
Feb’ 2020
|
-
2nd Rake of Smart ver-2 Humsafar Coaches dispatch
|
26th Jun’ 2020
|
-
1st LSLRD-AC-750 KVA coach dispatch
|
July’ 2020
|
|
4th Nov’ 2020
|
-
1st LSLRD AC-750 KVA (18711) coach dispatch for trial
|
Nov’ 2020
|
-
Flagging off of 1st ever Smart Tejas Sleeper Rake manufactured
|
27th Nov’ 2020
|
-
2nd Smart Tejas Sleeper & 3rd Tejas Sleeper Rake was dispatch WR
|
Jan’ 2021
|
-
4th & 5th Tejas Sleeper Rake was dispatch WR
|
Feb’ 2021
|
-
6th Tejas Sleeper Rake dispatch
|
Mar’ 2021
|
-
Total No. Of Coach’s Rolling Out Date 31.03.2021
-
Rolling out 7000th Coach
-
1st Rake of 12th Coach Dispatched for Mozambique
|
6645 coaches’
15th July 2021
October 2021
|
-
Vande Bharat Trainset (Shell) prototype model
|
31st March 2022
|
-
Rolling out of the 8500th Coach
|
31st March 2022
|
-
1st ACCNE (AC Economy) Coach turnedout
|
|
-
1st Rake of 3 Phase Cape Gauge DEMU (Exproted to Mozambique)
|
December 2022
|
-
Rani Girls Hockey Stadium
|
20.03.2023
|
-
Rolling out of the 9981 Coach
|
31st March 2023
|
-
1st Bharat Gaurav Tourist Train
|
02nd April 2023
|
-
Rolling out of the 10000th Coach
|
19th April 2023
|
-
130 KW Solar Power Plant Extention
|
23rd Aug 2023
|
-
GreenCo Platinum Rating Certificate
|
Sept 2023
|
-
Rolling out of the 11000th Coach
|
22nd Nov. 2023
|
-
5S Methodology Certificate
|
25th Nov. 2023
|
-
1st 3 Phase MEMU Train despatched
|
31st March 2024
|
-
Rolling out of the 11665th Coach
|
31st March 2024
|
-
Forge Wheel Plant takeover from Ministry of Ispat to MOR
|
1st April 2024
|
-
Rolling out of the 12000th Coach
|
24th June 2024
|
-
635 KW Roof top Solar Power Plant Extension on admin building
|
25th Oct 2024
|
-
Rolling out of the 13000th Coach
|
28th Dec, 2024
|
-
157.5 KW Roof top Solar Power Plant Extension on testing lab building.
|
27th Jan 2025
|