Milestones of MCF

 Milestone of Project 

 

Milestones

Foundation Stone Laid                                          

February 2007

Land Acquired                                                       

Aug 2007 to Aug 2009

Construction Work Commenced                          

May 2010

Commissioning of 33 KV Line                              

January 2011

Finishing and furnishing Shop completed

April 2011

1st Coach Furnished                                           

April 2011

Dedication of Factory to the nation

November 2012

1st Shell Assembly in MCF (Major Sub assemblies from RCF)

July 2013

1st LHB Shell From Raw material stage Onwards

August  2014

1st Bogie Manufacture in MCF                          

August  2014

Complete Bogie assembly                                

December  2014

Commissioning of 132 KV MRS                           

January  2015

100th Shell manufactured (SCN)                          

July 2015

Rolling Out 500th Coach                                       

February 2016

1st GS Shell manufactured                              

April 2016

1000th Coach Rolled Out

Dec, 2016

1st Humsafar Rake of the Indian Railway (22 Coaches)

Nov, 2016

1st Rake of Antyodaya Coaches dispatched     

April, 2017

 1st Power Car shell manufactured

May, 2017

1st Power Car Rolled out from MCF

Sept, 2017

2000th Coach Rolled Out May, 2018
1st  SMART Coach dispatched May, 2018
3000th Coach Rolled Out Jan, 2019
4000th Coach Rolled Out Aug, 2019
5000th Coach Rolled Out Feb, 2020
6000th Coach Rolled Out Nov ,2020
7000th Coach Rolled Out Jul.2021
8000th Coach Rolled Out Jan,2022
Total Coach Rolled Out Till 31st,March,2022 8520

 Milestones of the Modern Coach Factory

  • Nos of Coaches out in Year 2011-12 -   18      (All Bogies and Shells received from RCF/KXH)
  • Nos of Coaches out in Year 2012-13 -   70      (All Bogies and Shells received from RCF/KXH)
  • Nos of Coaches out in Year 2013-14 -   130    (All Bogies and Shells received from RCF/KXH) 
  • Nos of Coaches out in Year 2014-15 -   140    (20 Bogies and 95 Shells received from RCF/KXH)
  • Nos of Coaches out in Year 2015-16 -    285   (23 Shells received from RCF/KXH) 
  • Nos of Coaches out in Year 2016-17 -    576   (All Bogies and Shells manufactured at MCF)
  • Nos of Coaches out in Year 2017-18 -    711   (All Bogies and Shells manufactured at MCF)
  • Nos of Coaches out in Year 2018-19  -  1425   (All Bogies and Shells manufactured at MCF)
  • Nos of Coaches out in Year 2019-20 -   1930  (All Bogies and Shells manufactured at MCF)
  • Nos of Coaches out in Year 2020-21 -   1360 (All Bogies and Shells manufactured at MCF)
  • Nos of Coaches out in Year 2021-22 -   1875 (All Bogies and Shells manufactured at MCF)
  • Nos of Coaches out in Year 2022-23 -     1461  (All Bogies and Shells manufactured at MCF)
  • Nos of coaches out in year 2023-24-      141*(All Bogies and Shells manufactured at MCF)

             *Till 31,July 2023

 
 

 



Source : Welcome to Modern Coach Factory Raebareli Official Website CMS Team Last Reviewed on: 02-08-2023  

  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.